| Chapter | Start Date | End Date | Hrs. |
|---|---|---|---|
| Chap 1 - Planning and Preparation |
03/01/04 |
03/14/04 |
22 |
| Chap 4 - Bulkheads | 03/15/04 |
03/31/04 |
61 |
| Chap 5 - Fuselage Sides | 04/01/04 |
05/06/04 |
65 |
| Chap 6 - Fuselage Assembly | 05/07/04 |
06/13/04 |
93 |
| Chap 7 - Fuselage Exterior | 06/14/04 |
09/14/04 |
54 |
| Chap 8 - Headrests, Seat Belts, Heat Duct | (On
Hold) |
||
| Chap 9 - Landing Gear & Landing Brake | (On
Hold) |
||
| Chap 10 - R1145MS Canard | 09/15/04 |
11/07/04 |
68 |
| Chap 11 - Canard Elevators | 11/10/04 |
12/15/04 |
53 |
| Chap 12 - Canard Installation | (On
Hold) |
||
| Chap 13 - Nose, Nose Gear, Rudders | |||
| Chap 14 - Centersection Spar | 12/26/04 |
03/14/05 |
137 |
| Chap 15 - Firewall | |||
| Chap 16 - Control System | |||
| Chap 17 - Trim System / Center Console | |||
| Chap 18 - Canopy | |||
| Chap 19 - Wings & Ailerons | 03/21/05 |
||
| Chap 20 - Winglets & Rudders | |||
| Chap 21 - Strakes, Fuel Tanks | |||
| Chap 22 - Electrical | |||
| Chap 23 - Engine | 04/01/03 |
||
| Chap 24 - Covers & Fairings | |||
| Chap 25 - Finishing | |||
| Chap 26 - Upholstery | |||
| TOTAL HRS | 531 |